Update: Hoh Road

  • Fri Apr 2nd, 2021 1:38pm
  • News

Last week Interwest Construction Inc. (ICI) continued clearing trees in preparation for the new bridge installation at Canyon Creek, MP 10, and completed clearing of trees at the locations of the Engineered Log Jams at approximately MP 4.5.

This week, ICI will complete clearing trees for this year and will continue the installation of erosion control measures, temporary signage, and additional site preparation for the Canyon Creek bridge construction to begin later in April.

Impacts to Traffic:

• Temporary Traffic Control includes 1 lane flagger setups at the locations listed above on Upper Hoh River Road.

• Expect delays up to 30 minutes through the project limits (MP 3 through MP 11) between 7 a.m. and 4 p.m., weekdays.

• Olympic National Park and businesses along Upper Hoh River Road will remain accessible at all times during construction.